A feasibility model often brings together uncertain inputs, including yield, prices or rents, costs, timing and finance assumptions. A single base case can hide how dependent the conclusion is on those inputs. Sensitivity testing changes selected assumptions and shows how the model output responds. It is a way to understand exposure, not a forecast that a particular result will occur.
The useful question is not ‘what is the best number?’ but ‘which uncertain input would most change the decision?’ A site that only appears workable with a narrow value or cost assumption may need stronger evidence. A development finance professional can review the model design and explain whether the scenarios reflect the intended decision. Keep every input traceable to its source or label it as an assumption.
Select the assumptions worth testing
Start with the model’s decision drivers. These may include achievable sale values or rents, unit yield, construction and infrastructure costs, timing, vacancy or the cost of finance. Which matters most depends on the project. Ask the person preparing the model to explain why those inputs were selected and which are supported by market evidence, professional estimates or client assumptions.
Do not test every cell simply because the spreadsheet permits it. Focus on inputs that are both uncertain and consequential. A planning-dependent yield may deserve a different treatment from a minor administrative cost. If the source is weak, that uncertainty may itself justify a professional check before the model is refined further.
Change one input at a time
A first pass can vary one key input while holding others constant. This helps show whether the output is particularly responsive to rent, cost or timing. Record the baseline and each altered assumption. Explain why the chosen range is plausible, or state clearly that it is an illustrative stress test rather than an evidence-based range. Avoid choosing arbitrary changes that make the preferred case appear robust.
A simple table can show input, source, base assumption, alternative cases and resulting model output. The result should be labelled as a scenario, with date and version. If an input is held constant for the exercise, say so. That detail helps readers understand what the test isolates and prevents an illustrative calculation from being mistaken for a complete risk assessment.
Consider combined pressure carefully
Real pressures may occur together. A slower leasing period, higher costs and a delay in an approval could affect the same project, although the relationship and likelihood are not known from a spreadsheet alone. After testing separate inputs, consider a combined scenario that has a clear rationale. Explain why those items were grouped and whether the case is a stress test or a plausible alternative.
Avoid calling a combined downside case ‘worst case’ unless the scope defines what that means and why it is credible. Many factors may remain outside the model. A town planner, quantity surveyor or market professional can help identify uncertainty in their area, but no single specialist determines all project risks. Keep a written record of the assumptions discussed with each adviser.
Read the result, not just the output
The sensitivity table may show that a small change has little effect, or that one assumption materially shifts the result. Interpret that response in relation to the actual decision. If the decision threshold is crossed, identify whether new evidence could resolve the uncertainty. If no reasonable check can do so, parties may need to revise the concept or stop rather than continue polishing the model.
Model sensitivity does not describe the probability of outcomes. A scenario is not more likely because it is shown in a table. The evidence behind each range and the interaction between assumptions still require judgement. Do not present a high-case result as expected performance or use it to suggest a return is assured. Explain that the model is conditional and seek independent review where the decision is material.
Make the test reproducible
Keep the model version, date, input sources and scenario logic together. If a formula changes, record that as well. A reviewer should be able to understand how the output was produced without guessing which cells were adjusted. Where the work is prepared for a particular audience, identify whether they may rely on it and whether the author has agreed to that use.
This week, ask the model preparer to identify the three inputs that most affect the decision and show how the conclusion changes under reasoned alternatives. Ask a development finance professional to review the scenarios if the model will inform a material commitment. Use the exercise to choose the next evidence check, not to select the most favourable number for a presentation.
Questions on this
Does a sensitivity test show how likely a scenario is?
No. It shows how a model output changes when an input is varied. Likelihood requires separate evidence and judgement. State the purpose of each scenario and do not present an illustrative stress as a probability.
Should every assumption be varied at once?
Not initially. Changing one driver at a time can reveal its effect. A combined case may also be useful when there is a reasoned basis for the interaction. Record which inputs changed and why.